The bids received for the Ladyface Greenway Project on February 6, 2024, surpassed initial estimates, leaving minimal leeway for unforeseen circumstances. In a commitment to fiscal responsibility and adherence to budgetary constraints, the project team has redefined the project scope incorporating additional and deductive bid items. A revised bid package and Notice Inviting Bids (NIB) was released on Friday, March 15, 2024.
Updated Timeline
Contractor Bids Advertised | March 15, 2024 |
Pre-bid Job Walk | March 26, 2024 |
Bids Closed | May 7, 2024 |
Award Contract | May/June 2024 |
Notice to Proceed | July/August 2024 |
Construction Duration | 18 months (1 ½ years) |