The next phase of the Ladyface Greenway Project, following pile drilling, is the concrete pouring stage. In this step, concrete will be poured into the rebar structure to form the foundation and support elements of the bridge. This process will involve multiple concrete trucks on-site, and you can expect the sound of reverse beeping from the trucks as they maneuver.
Concrete pours are anticipated to continue, occurring up to three times a week, until the bridge piles are complete in Spring of 2025. This activity will generate noise and vibrations. Dust will be monitored and controlled at all times.
Details
- Activity: Concrete Pours for Bridge Pile Installation
- Start Date: October 28, 2024
- Duration: Approximately 8 months with concrete pours occuring up to three times a week.
- Typical Working Hours: 7:00 AM – 4:00 PM, MON to FRI *possible extended working hours and days with advance notification.
What To Expect
- Additional machinery, drilling rigs, and construction vehicles on site.
- Concrete trucks waiting, positioning, and backing (with beeping).
- Dump trucks moving soils from site to yard.
- Moderate disruption from construction noise and vibrations.
- Dust will be monitored and controlled at all times.
- Possible extended working hours and days.